CSBP Admin Drive & Truck Parking

Client

CSBP Limited

RJV Scope

Roadworks - Underground Services

Project Location

City of Kwinana

Project details

RJV have been awarded and tasked with upgrading the entry road into CSBP’s Kwinana facility as well as constructing new truck parking laydown areas. RJV have carefully staged roadworks to comply with CSBP’s requirements to maintain 24 hour access into their facility. 

RJV have developed and employed a rigorous permit to dig system to accommodate the many buried critical services – both known and unknown – in the works area. Works commenced in August and are anticipated to be completed by November, the short 12 week timeframe is mandated by CSBP to minimise disruptions to their critical facility.