Boddington
Client
Newmont
Total Project Value
$28M
RJV Scope
Waste Dump Expansion
Project Location
Boddington, Western AustraliaProject details
Construction of 300 HA Waste Dump at the Boddington Gold Mine for Newmont.
Contract value of $28M with duration of two years that commenced in March 2016.
Scope of Work was bulk earthworks including:
- clearing,
- construction of drains
- mining of gravel
- construction of mine water and run-off dams
Areas within the construction site had been determined as Dieback areas requiring strict control over machine movements within the site and plant cleaning when moving from one zone to another.